最近有两名团队成员因为客户削减预算而从一个项目中释放出来。然而,敏捷团队收到的工作需求仍然和以前一样,甚至更多。敏捷项目负责人应该如何解决这种情况?Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before. How should the agile project leader resolve this situation?


A.用新的团队容量更新限制日志。Update the restriction log with the new team capacity.

B.向团队解释新的项目需求。Explain the new project requirements to the team.

C.与释放的团队成员一起更新项目预算。Update the project budget with the released team members.

D.向客户解释新的团队速度。Explain the new team velocity to the customer.


知识点:PMP冲刺题


参考答案:D


解析:敏捷项目中,每次冲刺的工作量是根据团队速度进行规划的,人员的减少会导致速度降低,但工作量的不变甚至增加了,项目经理应该向客户说明情况,选D。选项B错误,在敏捷项目中,产品负责人(Product Owner)负责理解和解释需求。选项AC错误,不能解决问题。