一个项目有一个质量管理计划。该计划规定,项目可交付成果必须在截止日期前至少五个作日进行质量评审。有四个交付品不符合质量要求。项目经理应该怎么做? A project has a quality management plan in place.This plan states that project deliverables must be reviewed for quality at least five business days before the deadline. Four deliverables have failed the quality requirement.What should the project manager do?
A.生成一个因果图进行分析。 Generate a cause-and-effect diagram for analysis.
B.重写质量管理计划的相关部分。 Rewrite relevant portions of the quality management plan.
C.询问对项目进行内部审计的可行性。 Inquire regarding the feasibility of an internal audit of the project.
D.联系项目发起人并请求建议。 Contact the project sponsor and request advice.
参考答案:A
解析:因果关系图将问题的原因分解为离散的分支,能帮助确定主要原因或根本原因。