“微信扫一扫”进入"可可试卷"微信小程序刷题

项目管理专业人士资格认证(PMP)题库(1459题)


由于市场条件的变化,原始项目需求的商业价值发生了变化。项目经理在执行阶段应考虑什么?Due to a change in market conditions, the business value for the original project requirements has c hanged. What should the project manager consider for execution?


A.评估并处理小需求,以交付商业价值。Evaluate and work on small requirements to deliver business value.

B.与干系人协商,以使用现有的商业价值进行交付。Negotiate with the stakeholder to deliver with existing business value.

C.按计划继续,因为变更对项目没有影响。Continue as planned since changes will have no impact on the project.

D.考虑商业价值修改后的需求。Take into consideration the requirements with the modified business value.


知识点:PMP冲刺题


参考答案:D


解析:PMBOK 7th,2.1-创造价值,P8。创造价值的一个典型方式就是“创造满足客户或最终用户需要的新产品、服务或结果”,因此当执行阶段原始的项目需求发生变化时,应该积极调整和及时响应,为最终能够交付价值而努力。