一个团队即将完成一个部署,并正在等待客户提供关键信息。客户不断推迟发送信息,这导致部署进度延迟。项目经理应该做些什么来防止延迟?A team is about to close a deployment and is waiting to receive critical information from the customer. The customer continues to postpone sending information, which is consequently delaying the deployment. What should the project manager have done to prevent the delay?
A.将任务委派给产品负责人。Delegated the task to the product owner.
B.要求团队使用样例数据。Asked the team to use the sample data.
C.向发起人提出并寻求他们的支持。Engaged the sponsor and sought their support.
D.提前获取所有关键信息。Received all key information ahead of time.
参考答案:D
解析:关键词“客户不断推迟发送信息”,且问题是为防止延迟,即项目经理应该事先做什么,D选项最佳,提前识别并收集项目执行所需的所有关键信息。