项目管理专业人士资格认证(PMP)题库(1459题)


一个计划在四个月内执行的项目被分为八个迭代。在第一次回顾中,团队意识到只有一个成员有经验做一个关键的项目需求。项目经理应该怎么办?A project defined to be executed in four months is divided into eight iterations. During its first retrospective, the team realizes that only one member has experience doing a key project requirement. What should the project manager do?


A.邀请团队成员在下一次回顾中分享经验。Invite the team member to share experience in the next retrospective.

B.请求发起人增加具有所需经验的团队成员。Ask the sponsor to add team members with the required experience.

C.在团队内计划知识共享会议。Plan knowledge-sharing sessions within the team.

D.请求发起人为团队提供培训课程。Ask the sponsor for a training course for the team.


知识点:PMP冲刺题


参考答案:C


解析:敏捷实践指南,4.3.1-敏捷团队,P39。在成功的敏捷团队中,团队成员在工作中以各种方式开展合作(如结对、群集、群体开发)。因此当团队只有一个成员具备经验和特定技能时,可以通过合作的形式,进行知识共享和能力复制,使更多的团队成员具备该技能,从而提升团队的整体技能水平。