一个组织启动了一个新项目,该组织在其组织治理过程中定义了监管要求,项目经理应该如何定义项目治理?A new project needs to be kicked off in an organization that has regulatory requirements defined in their organizational governance process. How should the project manager define the project governance?


A.询问项目管理办公室(PMO)是否可以忽略监管要求。Ask the project management office (PMO) if the regulatory requirements can be ignored.

B.更新项目治理,以包括当前的监管要求。Update the project governance to include the current regulatory requirements.

C.自定义所有监管要求,以适应特定的项目治理。Customize all of the regulatory requirements to fit within the specific project governance.

D.更新部分监管要求,以适应项目治理。Update some of the regulatory requirements to fit within the project governance.


知识点:PMP冲刺题


参考答案:B


解析:PMBOK 6th,2.2-事业环境因素-组织内部的事业环境因素,P38。“组织文化、结构和治理”都是属于项目的事业环境因素,是项目管理的重要输入。因此在定义项目治理的过程中,必须要包括组织定义的监管要求。最佳选项B。