项目经理被供应商告知,由于监管变更,即将出现原材料短缺。项目经理该怎么做? A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?
A.告诉供应商他们有义务提供原材料。 Tell the supplier that they have an obligation to supply the raw material.
B.寻找能够按时交付相同材料的新供应商。 Search for a new supplier that can deliver the same materials on time.
C.征求法律部门的意见并执行处罚。 Seek advice from the legal department and implement penalties.
D.评估原材料短缺对项目的可能影响。 Assess the possible impact of the raw material shortage on the project.
参考答案:D
解析:选D,项目经理得知即将到来的原材料短缺,第一步应该是评估对项目的可能影响。该影响分析应包括评估项目原材料的关键性、所需材料的数量和交付时间表。根据分析,项目经理可以制定计划来减轻影响。