“微信扫一扫”进入"可可试卷"微信小程序刷题
项目经理正在领导一个处于高级阶段的项目。风险管理计划中所识别的所有高层级风险均已解决,对项目不再构成风险,只有低层级风险仍然存在,项目经理现在应该做什么?A project manager is leading a project that is in an advanced stage.All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project.Only low-level risks remain. What should the project manager do now?
A.降低项目风险的优先级,因为所剩余风险均为低层级风险。Reduce the priority of project risks as all remaining risks are low-level.
B.对己识别的风险重新评估,并更新风险登记册。Reevaluate identified risks and update the risk register.
C.通知干系人所有高层级风险均已解决。Notify stakeholders that all high-level risks have been resolved.
D.将低层级风险重新归类为高层级风险。Reclassify low-level risks as high-level risks.
参考答案:B
解析:《PMBOK》第6版453页,11.7-监督风险。风险在项目实施过程中处于动态变化,所以在识别出风险后不能置之不管。因此,需要对项目所可能面对的风险进行持续的跟踪和监督,更新风险所发生的概率和影响,这些变化要在风险登记册上有所体现,B选项正确。选项A,对风险等级的调整,要经过正确的评估,而不能凭借主观感受擅自调整。选项C,根据风险管理计划中的报告方式,可以向关键干系人进行通报,但是未经正确评估既通报,欠妥。选项D,同A,错在擅自调整了风险的等级。