项目经理收到团队成员提出的在不影响进度或成本的情况下改进产品属性的建议。这将为项目和客户增加价值。项目经理应该怎么做? A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do?
A.拒绝该建议,并要求团队成员集中精力执行该计划Reject the suggestion and ask the team member to focus on executing the plan
B.要求团队成员提交一个正式的变更请求 Ask the team member to submit a formal change request
C.接受这个建议,因为它对项目没有影响 Accept the suggestion as it has no impact on the project
D.请另一个团队成员验证该建议的影响Ask another team member to validate the impacts of the suggestion
参考答案:B
解析:考点:实施整体变更控制 来源:PMBOK6th,4.6-实施整体变更控制,P113-115 描述:在整个项目生命周期的任何时间,参与项目的任何干系人都可以提出变更请求。一旦确定了项目基准,就必须通过本过程来处理变更请求。 解析:项目正在进行,范围、进度、成本基准已经确定,对于干系人提出的改进产品属性的建议,需要通过实施整体变更控制过程来进行。选B正确