项目经理正在管理一个处于执行阶段的项目,交付成果的质量标准被正式接受。然而,一个政府机构最近引入了新标准,可能对该项目产生重大影响。必须更改以符合新的质量标准。项目经理应该怎么做? A project manager is managing a project that is halfway through its execution phase, and the quality standards of the deliverables were formally accepted. However, a government agency has recently introduced new standards that may signifi cantly impact the project. The deliverables must be changed to align with the new quality standards. What should the project manager do?
A.安排项目团队对政府机构引入的新规定进行培训 Schedule training for the project team on the new regulations introduced by the government agency
B.建立一个结构化的、独立的流程,以确定项目活动是否遵循了这些标准 Set up a structured, independent processes to determine if project activities followed the standards
C.更新经验教训,并通知高级管理人员新标准 Update the lessons learned register and inform senior management of the new standards
D.评估新法规对项目的影响,并提交变更请求 Evaluate the impact the new regulations will have on the project and submit a change request
参考答案:D
解析:解析:“必须更改以符合新的质量标准”,明确说了政府新标准导致质量标准发生了变化,合规大于天,先评估影响再执行,D比B更全面。