在有两个团队(A和B)的项目的第二次迭代中,项目经理担心来自团队A的两个关键活动必须在第四次迭代中启动。此外,这两个活动依赖于B团队尚未确定优先级的活动。项目经理应该怎么做? During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized. What should the project manager do?
A.取消当前迭代,并根据依赖活动重新安排顺序。 Cancel the current iteration and reschedule it with the dependent activity.
B.在团队B的当前迭代中包含相关的活动。 Include the dependent activity in the current iteration for team B.
C.确保团队B在第三次迭代中优先考虑相关活动。 Ensure team B prioritizes the dependent activity in iteration three.
D.在第二次迭代中将两个关键活动分配给团队B。 Assign the two critical activities to team B in iteration two.
参考答案:C
解析:来源:PMBOK6th,6.5.3.1-项目进度计划 P217 描述:为各个相互关联的活动标注了计划日期,持续时间,里程碑和所需的资源。 解析:确保团队B在第三次迭代中对依赖的活动进行优先排序。这是因为这个选项符合过程域的目标,即制定并执行有效的进度管理计划。