在项目执行期间,项目经理注意到只有一个团队成员拥有构建产品所需的一项技术技能。项目经理担心这可能会对质量和进度产生影响,因为大多数即将到来的活动将需要至少三个具有这种特定技能的人。项目经理应该采取哪两项行动来防止团队不合格?(选择两个)During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product. The project manager is afraid this might have a future impact on the quality and schedule, because most of the upcoming activities will require at l east three people with this specific skill.What two actions should the project manager take to prevent the team from being unqualified? (Choose two)


A.从路线图中排除活动Exclude the activities from the roadmap.

B.鼓励结对工作和知识分享Encourage pair work and knowledge sharing.

C.教授整个团队新技能Teach the entire team the new skill.

D.与外部培训师一起组织培训活动Organize the training activities together with the external trainers.

E.增加对需要这些能力的活动的时间估算Increasing temporal estimates of activities that require these abilities.


知识点:考前必刷题


参考答案:BD


解析:选项B正确:通过鼓励团队成员结对工作,并促进他们之间的知识共享,可以提高整个团队的技能水平。团队成员可以相互学习,共同解决问题,并增加对特定技能的掌握程度。这有助于减轻依赖于单个团队成员的风险,并增强整个团队的技术能力。选项D正确:如果团队缺乏特定的技能,项目经理可以组织一个培训活动,并邀请外部培训师来传授所需的技能。培训可以提供新的知识和技能,帮助团队成员提高能力,并满足项目需求。选项C不是最佳选项,活动需要至少三个具有这种特定技能的人,培训整个团队可能会导致时间和资源的浪费。