一个项目经理被分配到一个长期项目。这位项目经理遇到了政府关于一项可能影响项目的新法律的辩论。项目经理应该采取的前两项行动是什么?(选择两个)A project manager has been assigned to a long-te rm project. The project manager came across a government debate over a new law that may affect the project. What are the first two actions the project manager should perform?(Choose two)


A.创建变更请求,与变更控制委员会(CCB)讨论。Create a change request to discuss with the change control board(CCB).

B.请求追加紧急情况预算。Request additional budget for contingency.

C.与项目团队一起执行风险识别过程。Perform a risk identification process with the project team.

D.与项目干系人协商。Consult with the project stakeholders.

E.与主题问题专家(SMEs)讨论可能的影响。Discuss the possible impacts with subject matter experts(SMEs).


知识点:考前必刷题


参考答案:CE


解析:关键词“一项可能会影响项目的新法律的辩论”,意味着这是一个风险,需要先进行分析评估影响,再规划应对策略并执行。选项CE最佳。