一个项目与同一组合中的其他项目进行衔接,这些项目正在国际地区开发。其中一个国际项目建议在这个项目中实施一项战术性变更。项目经理接下来应该怎么做?A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project. What should the project manager do next?


A.利用团队与国际同事的联系,及早获得未来变更的警告。Use the team's connections with international colleagues to get early warnings on future changes.

B.在变更经过变更控制过程时,保持关注优先事项。Keep the focus on the priority items while the change goes through the change control process.

C.拒绝变更请求,因为它可能对项目绩效产生负面影响。Reject the change request since it may negatively impact the project's performance.

D.尽快实施变更请求,以避免累积新的范围。Implement the change request as soon as possible to avoid accumulating new scope.


知识点:考前必刷题


参考答案:B


解析:根据整体变更控制程序,在处理变更请求时,项目经理应该先对变更进行评估并申请批准,同时保持对项目优先事项的关注,有助于确保变更请求与项目的目标和范围一致。选项B最佳。