一位项目经理正在进行一个项目,以建造一个制造综合体。该项目将分三个阶段进行:工程、采购和施工。采购阶段处于启动阶段。项目发起人希望按照计划执行项目阶段,但也希望适应和调整新数据、来自客户的输入,以及在项目进展的各个阶段中的变更。项目经理应该如何处理这个项目?A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses. How should the project manager approach this project?
A.应用预测型项目管理方法。Apply a predictive project management approach.
B.评估并决定分阶段的项目管理方法。Evaluate and decide on a phased project management approach.
C.实施适应性的项目管理方法。Implement an adaptive project management approach.
D.使用混合模型将预测生命周期和适应生命周期相结合。Use a hybrid model to combine predictive and adaptive life cycles.
参考答案:D
解析:根据题干,发起人既希望按计划完成,又希望能适应调整和客户输入,结合预测和适应性生命周期的混合模型最合适该项目。