在一个项目会议期间,项目经理要求各风险责任人演示可能影响待办事项的问题。在演示过程中,项目经理意识到一些风险责任人没有实施已经商定的风险应对措施。项目经理应该做些什么?During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses. What should the project manager do to reduce exposure?
A.将这些风险责任人报告给项目管理办公室(PMO),并建议将其从团队中移除。Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.
B.将未完成的风险任务重新分配给已实施风险应对的其他团队成员。Reassign the outstanding risk tasks to other team members who have implemented their risk responses.
C.要求这些风险责任人在下次会议之前实施风险应对措施,并在会议上介绍结果。Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.
D.与这些风险责任人私下会面,并与他们合作解决风险应对的任何障碍。Meet privately with the risk owners and work with them to address any impediments to the risk responses.
参考答案:D
解析:先沟通了解分析问题原因,再讨论解决方案并执行,选D。