项目管理专业人士资格认证(PMP)题库(1459题)


项目经理正在管理一个新的开发计划,以使某些技术功能自动化。在项目启动期间,项目经理表示需要技术架构师在适当的时间内支持项目。项目发起人将现有的技术架构师告知项目经理,该架构师拥有有价值的知识,但是已经被分配到项目组合级别。项目经理应该为技术架构师角色使用什么参与模型来确保项目成功?A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level. What engagement model should the project manager use for the technical architect role to ensure project success?


A.聘请一个新的技术架构师,他将完全致力于当前的项目。Hire a new technical architect who would be solely dedicated to the current project.

B.共享现有的技术架构师,以便他们可以分配到当前项目和其他项目。Share the existing technical architect so they can be allocated to the current project and other projects.

C.雇用一个新的技术架构师,他将在当前项目和其他项目之间分担工作。Hire a new technical architect who will share work between the current project and other projects.

D.指派现有的技术架构师专门负责当前的项目。Assign the existing technical architect to solely be dedicated to the current project.


知识点:考前必刷题


参考答案:B


解析:项目组合中各项目优先度相同,“分配到项目组合级别”是指资源是支持一系列相关项目共同使用。因此选项B正确。 选项A,将增加当前项目成本。选项C,将增加项目组合的成本。选项D,项目发起人已声明此资源已分配到项目组合级别。