一项新的可再生能源项目的初步可行性研究即将获得批准。为了确保项目时间进度得以维持,必须在初步可行性研究获得批准的同时,继续进行与可行性研究相关的活动。项目经理应该如何操作?A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved. How should the project manager proceed?
A.在等待最终批准时,同时进行初步可行性研究和可行性研究。Proceed with both the prefeasibility and feasibility studies in parallel while waiting for the final approvals.
B.将可行性活动纳入初步可行性研究中,并申请变更项目范围和预算。Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.
C.在初步可行性研究获得批准的同时,获得许可进行可行性研究作为并执行活动。Obtain approval to proceed with the feasibility study as a parallel activity while the prefeas bility study is approved.
D.在进行可行性研究活动之前,确保初步可行性研究得到批准。Secure approval of the prefeasibility study before proceeding with the feasibility activities.
参考答案:C
解析:根据题干,“初步可行性研究即将获得批准”,为了保持项目时间线,项目经理应该先寻求许可,在初步可行性研究获得批准的同时进行可行性研究,这样可以确保项目进度,同时遵守必要的批准和评审过程,选C。选项A缺乏必要的审批过程。选项B可能导致初步可行性研究的范围扩大,并导致预算增加。选项D错误,等到初步可行性研究批准才开始可行性研究,会影响到项目的时间线。