一个项目经理正在规划一个项目,并发现特定项目任务的立法要求将会发生变化。这将发生在项目执行阶段进行到一半的时候,并将影响几个关键工人的许可证,使其不符合要求。项目经理应该怎么做?A project manager is planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution phase and will affect a few key workers' licenses, which will become noncompliant. What should the project manager do?
A.立即开始为关键工人安排培训,以确保符合要求。Start scheduling the training for key workers now to ensure compliance.
B.保留当前的关键工人,因为项目已经开始。Maintain the current key workers since the project has already started.
C.更新项目章程,以确保新的立法要求得到满足。Update the project charter to ensure that new legislative requirements are met.
D.启动新工人的招聘活动,以满足许可证要求。Start a recruitment drive for new workers with the licenses required.
参考答案:A
解析:选项A,马上安排培训,以确保符合要求。属于主动遵守法规,为最佳答案。选项B,这种风险应对方式,会将风险隐患保留在项目内。选项C,更新章程,无法解决工人许可证现状不合规的情况。选项D,题干所指工人为关键工人,新工人的工作效果未知,并使项目成本增加。