网络安全团队通知技术项目的项目经理,政府的网络安全要求发生了变化。项目经理召开团队会议讨论需求,团队了解到可以在不增加成本的情况下进行设计更改。项目经理应该指导团队做什么?The cybersecurity team informed the program manager of the technology program that the government's cybersecurity requirements had changed. The project manager held a team meeting to discuss the requirements, and the team learned that design changes could be made without increasing costs. What should the project manager direct the team to do?
A.更新范围管理计划以跟踪新的政府要求。Update the scope management plan to track the new government requirements.
B.接受网络安全团队的请求,因为公司的安全存在不合规的风险。Accept the cybersecurity team's request as the security of the company is at risk of being noncompliant.
C.要求项目发起人增加应急储备资金,以降低风险。Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.
D.通过变更控制流程请求变更,以管理新的网络安全要求。Request changes through the change control process to manage new cybersecurity requirements.
参考答案:D
解析:根据题干,合规需求发生了变化,即使并不影响成本,也应该通过变更控制流程进行正式的管理,这确保了变更的影响得到了适当的评估和记录,并通知了干系人,选D。