一个项目已经到了结束阶段。工作基本上已经完成,项目经理想要开始项目的关闭过程。项目经理应确保在开始结束过程之前什么已经到位?A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?


A.组织过程资产(OPAs)已被更新。The organizational process assets (OPAs) have been updated.

B.项目的合同交付物已被接受。The contractual deliverables of the project have been accepted.

C.交接和交付物验收都已经完成。The handover and deliverable acceptance have been completed.

D.学习经验会议已经进行。The lessons learned sessions have been conducted.


知识点:考前必刷题


参考答案:C


解析:PMBOK 6th,6.1-结束项目或阶段,P634。在结束项目或阶段,项目经理需要确保最终产品、服务或成果移交,选C。选项B没有C全面。