产品待办事项列表已经完成并确定了优先级。第一次冲刺已经开始。在每日站会期间,一名团队成员告知签订外部供应商合同会有延迟。在这种情况下,项目经理的优先级是什么?The product backlog has been completed and prioritized. and the first sprint has begun. A team member advised that during the daily standup there is a delay in having an external vendor contract signed. What is the project manager's priority in this situation?


A.要求团队成员尽快签订合同Request that the team member gel the contract signed as soon as possible

B.确定缓解策略以推动项目向前发展Identify mitigation strategies to move the project forward.

C.为团队成员接管合同谈判,以加快进程Take over contract negotiations for the team member to speed up the process.

D.协助清除障碍因素和障碍,使项目能够继续进行Assist with the removal of impediments and blockers so that the project can continue.


知识点:考前必刷题


参考答案:D


解析:敏捷项目中,项目经理作为仆人式领导,职责之一就是帮助团队扫清障碍,选D。选项C不恰当,扫清障碍并不是直接帮团队成员做本该团队做的工作。选项A错误,只这是命令和控制的方法。选项B,只是缓解策略,没有解决问题。