当项目团队在每个冲刺中向客户交付增值特性时,他们表现得非常好。然而,他们文档有所缺失,项目经理必须找到一种方法来确保文档保持最新。项目经理应该采取什么行动?A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current. Which action should the project manager take?


A.创建一个特定的冲刺来交付项目文档。Create a specific sprint to deliver the project documentation.

B.在项目期间分配一个专用资源来处理文档。Assign a dedicated resource to work on the documentation during the project.

C.将文档作为已完成定义(DoD)中的一个标准部分。Make documentation a standard part of the d efinition of done(DoD).

D.在功能交付后,再关注文档。Focus on the documentation alter the features are delivered.


知识点:考前必刷题


参考答案:C


解析:敏捷项目管理更重视工具,不代表不需要文档,而是强调合适的文档,比较好的做法就是把文档的完成作为DoD的部分,而不是单独补充,选C。在敏捷方法中,已完成定义(DoD)代表了用户故事或任务必须满足的标准,才能被认为是“完成”。