项目团队的业绩在最近三个迭代中有所下降。一些团队成员感到失望,并在回顾会议上提出他们的担忧。项目经理应该怎么做?A project team's performance has declined for the last three iterations. Some of the team members are disappointed, and raise their concerns during the retrospective meeting. What should the project manager do?
A.关注矫正问题而非仅仅纠正表面症状。Focus on remediation not merely on correcting symptoms.
B.将团队的表现与其他项目团队进行比较。Compare the team's performance against othe rproject teams.
C.根据迭代工作量确定潜在的故障点。Identify potential failure points based on the teration workload.
D.激励团队表现得更好。Motivate the team to perform better.
参考答案:A
解析:在多次迭代中性能下降意味着可能潜在问题,项目经理应该致力于识别根本原因并解决,选A。