项目经理被要求实施一种混合方法,该方法将取代即将到来的项目的预测方法。项目经理应如何相应地调整其职责?A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project. How should the project manager adjust their responsibilities accordingly?


A.支持团队合作,消除障碍因素,成为服务型(仆人型)领导者。Become a servant leader by supporting team collaboration and removing impediments.

B.将协调活动委派给产品负责人,以便项目经理能够进行协作管理。Delegate coordination activities to the product owner so the project manager can locus on managing collaboration.

C.要求Scrum主管专注于协作,而项目经理专注于协调。Request a scrum master to focus on the collaboration while the project manager focuses on the coordination.

D.向项目团队成员介绍新的沟通工具。Introduce new communication tools to the project team members.


知识点:考前必刷题


参考答案:A


解析:项目方式由预测型转变为混合型,则需要增加敏捷相关内容,敏捷推崇自组织团队、仆人式领导,A项最符合混合项目管理方法。