一个关键的项目里程碑被错过了,因为一个团队成员没有按时完成任务。这在终端用户的演示中引起了一场激烈的讨论。项目经理下一步该怎么做?A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users. What should the project manager do next?
A.与团队成员一对一地讨论这个问题。Discuss the issue with the team member in a one-on-one meeting.
B.在团队会议上要求团队成员解释延迟的原因。Ask the team member to justify the delay during a team meeting.
C.审查人力资源(HR)政策,以采取相关的纠正措施。Review the human resources (HR) policies for relevant corrective actions.
D.将绩效问题上报给团队成员的职能经理。Report performance issues to the functional managers of team members.
参考答案:A
解析:出现团队个体初次发生问题时,应该单独一对一沟通,了解产生问题的原因,尊重团队个体成员,选A。且与团队成员单独讨论这个问题将提供讨论延迟原因的机会,项目经理可以确定任何必要的纠正措施,使项目重回正轨,并确保团队成员理解履行承诺的重要性。选项B,在团队会议上要求团队成员解释,可能会导致公众批评或团队成员的尴尬。