一个新的项目经理正在为一个软件开发公司制定时间敏感的社交媒体策略,并为干系人制定沟通管理计划。自从公司转向全职远程工作以来,这是第一个主要的项目。在审查所有之前的公司文献后,项目经理发现了一个标准操作程序(SOP)文档,概述了所有沟通应如何进行。项目经理应该如何处理?A new project manager is working on a time-sensitive social media strategy for a software development company that is building a communications management plan for the stakeholders. This is the first major project since the company shifted to working remotely on a fulltime basis. After reviewing all previous company artifacts, the project manager finds a standard operating procedure (SOP) document outlining how all communication shouId take place. How should the project manager poceed?


A.遵循项目的SOP,记录所需的更改,并上报至变更管理委员会。Adhere to the SOP for the project, make a note of required changes, and escalate to the change management board.

B.使用SOP作为基础计划,并在项目的控制和监控阶段进行更新。Use the SOP as a base plan and make updates during the control and monitoring phase of the project.

C.忽略SOP,为这个项目写一个单独的沟通管理计划。Ignore the SOP and write a separate communications management plan for this project.

D.评估SOP的相关性,进行更新,并在项目规划期间征求干系人的意见。Assess the SOP for relevancy, make updates, and circulate to the stakeholders for comment during project planning.


知识点:考前必刷题


参考答案:D


解析:考虑到公司已转向全职远程工作,过去的SOP可能不再完全适用。因此,项目经理应该评估SOP的相关性,根据当前项目情况进行必要的更新,并确保与所有干系人的需求和期望保持一致,选D。