在执行阶段,项目经理正在检查问题日志,并发现仍有未解决的高优先级问题。大多数开放问题需要项目团队之外的外部领域专家的努力。项目经理应该怎么做?During the executing phase, a project manager is reviewing the issue log and finds there are outstanding high-priority issues that are still open. Most of the open issues require effort from external do main experts who are not on the project team. What should the project manager do?
A.请问题报告者关闭问题,因为没有项目团队成员具有所需的领域知识。Ask the issue reporter to close the issues, because there are no project team members who have the required do main knowledge.
B.与问题报告者一起审查未决问题。Review the open issues with the issue reporter and issue a change request to hire an external domain expert.
C.要求项目团队成员学习所需的领域知识,并在短时间内解决尚未解决的问题。Request that the project team members learn the required domain knowledge and resolve the open issues in a short time.
D.缩减项目范围,以确保项目小组具备按时交付系统的知识。Reduce the project scope to ensure that the project team has the knowledge to deliver the system on schedule.
参考答案:B
解析:排除法,选项B最佳。选项A不解决问题。选项C,学习可能需要大量时间,导致项目进度延误。选项D不是最佳解决方案,缩小项目范围会影响项目的目标、质量和干系人的要求。