项目经理正在进行一个软件开发项目。项目经理和项目团队识别了项目风险。随着项目的进展,其中一个风险实现了,项目经理参考了风险管理计划,以确定如何管理风险。一旦选择并实施了风险管理策略,风险就被关闭了。问题是:项目经理在什么时候将风险从风险登记册移到问题日志?A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed. At what point did the project manager move the risk from the risk register to the issue log?


A.风险监控Risk monitored

B.风险发生Risk occurred

C.风险管理Risk managed

D.风险识别Risk identified


知识点:考前必刷题


参考答案:B


解析:当风险发生时,它就从风险转变为实际问题,选B。