“微信扫一扫”进入"可可试卷"微信小程序刷题

项目管理专业人士资格认证(PMP)题库(1459题)


项目发起人已经批准了项目章程和商业论证。项目经理审查了启动项目的文档,但不清楚项目预期的收益是否与企业的战略目标相符。项目经理应首先做什么?A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business. What should the project manager do first?


A.开始执行项目,因为领导要对商业战略负责。Start executing the project since leadership is responsible for the business strategy.

B.与项目发起人会面,以更好地了解项目的战略利益。Meet with the project sponsor to better understand the strategic benefits of the project.

C.提出更符合业务战略的最新商业论证和项目章程。Propose an updated business case and project charter that are more aligned with the business strategy.

D.进行定性和定量的风险分析,并将结果记录在风险登记册内。Conduct qualitative and quantitative risk analysis and record the results in the risk register.


知识点:考前必刷题


参考答案:B


解析:关键词“不清楚项目预期的收益是否与企业的战略目标相符”,为直接解决问题,首先需要了解项目商业价值和战略利益,选B。