项目经理正在与客户举行一个进度会议。客户要求进行设计变更,这可能为项目增值。项目经理应该采取什么行动?A project manager is attending a progress meeting with a client. The client requests a design change which might potentially add value to the project. What action should the project manager take?
A.咨询团队成员并允许他们做出决策。Consult with team members and allow them to make a decision.
B.适应变更请求以满足客户的需求。Accommodate the change request to serve the client's needs.
C.说服客户不要对项目作出变更。Convince the client not to make changes to the project.
D.做出专注于项目目标的事务性决策。Make transactional decisions focusing on the project goals.
参考答案:D
解析:采用排除法,AB错误,变更需要走变更流程,范围变更是CCB审批;选项C直接拒绝变更不对。 选项D最佳,当干系人提出变更请求时,项目经理应考虑该变更对项目目标和整体计划的影响。