在一个混合项目的执行过程中,不得不更换一个开发人员。新资源在质量保证任务上极其胜任,但在开发上却没有太多经验。项目经理该怎么做?During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much experience in development. What should the project manager do?


A.允许团队重新评估任务并决定如何分配任务。Allow the team to reevaluate the tasks and determine how they should be allocated.

B.保持相同的任务分配结构,以避免项目团队中的任何中断。Maintain the same task allocation structure to avoid any disruption in the project team.

C.将开发人员转移到另一个团队,寻找替代开发人员。Move the developer to another team and look for a replacement developer.

D.请求将所有质量保证任务分配给新的资源。Request that all quality assurance tasks be allocated to the new resource.


知识点:考前必刷题


参考答案:A


解析:混合项目环境,通常是自组织团队,即团队成员自己决定谁做什么,而不是项目经 理决定,选A。