敏捷项目正在运行六个迭代中的第二个。一个没有敏捷经验的新团队成员刚刚加入团队。在每日会议中,项目经理发现团队在实现目标时遇到问题。项目经理应该怎么做?An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals. What should the project manager do?


A.向团队提供反馈,并召开会议审查团队规则。Provide feedback to the team and hold a meeting to review team rules.

B.向团队提供反馈,并召开回顾会议,找出根本原因。Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.向团队提供反馈,并要求对新成员进行敏捷培训。Provide feedback to the team and request agile training for the new member.

D.向团队提供反馈,并指导新的团队成员使用敏捷方法论。Provide feedback to the team and coach the new team member in agile methodology.


知识点:考前必刷题


参考答案:B


解析:关键词“团队在实现项目目标时遇到了问题”,问题不明要先了解情况,可以通过回顾会议进行问题识别,并讨论解决方案,选B。选项C和D错误,有问题并非就是新员工导致的。