“微信扫一扫”进入"可可试卷"微信小程序刷题

项目管理专业人士资格认证(PMP)题库(1459题)


一个项目团队在故事大小不合适的情况下完成了很多次迭代。在一些迭代中,团队对一些故事进行了大小调整,并提前完成它们。在其他迭代中,团队确定了故事的大小,但无法完成计划的活动。在计划下一个迭代的过程中,团队应该做些什么不同的事情?A protect team has completed many iterations wit hout proper sizing of the stories. In some iterations the team sized some stories and completed them ahead of time. In other iterations the team sized the stones but was unable to complete the plan ned activities. What should the team do differently during planning for the next iteration?


A.要求产品负责人和团队协调人提供故事的大小Request the product owner and team facilitator to provide the size of the story

B.平均每个团队成员为一个故事提供的故事点Average the story points provided by each team member for a story

C.继续多轮计划扑克,得出故事的大小Continue multiple rounds of planning poker and arrive at the size of the story

D.与不同的团队合作,得出故事的规模Collaborate with different teams and arrive at the size of the story


知识点:考前必刷题


参考答案:C


解析:计划扑克/估算扑克(Planning Poker)是一种敏捷评估技术,整个团队协作来评估用户故事的相对大小,通过持续多轮的计划扑克,团队可以确保他们对每个故事所需的复杂性和工作量有共同的理解,这有助于为下一次迭代更好地规划和分配工作。