项目团队向客户交付了关键的可交付物。客户抱怨没有包括维修手册。项目经理下一步该怎么做?A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included. What should the project manager do next?
A.提交一份包括手册的变更请求。Submit a change request to include the manual.
B.添加所需的手册并更新风险日志。Add the needed manual and update the risk log.
C.审查干系人参与计划。Review the stakeholder engagement plan.
D.审查合同的条款和条件。Review the terms and conditions of the contract.
参考答案:D
解析:关键词“客户抱怨没有包括维修手册”,项目经理应该首先核实项目范围,查看之前签订的合同条款,是否包含维修手册。