“微信扫一扫”进入"可可试卷"微信小程序刷题

项目管理专业人士资格认证(PMP)题库(1459题)


一个敏捷项目有一个记录在案的需求清单,按高、中、低类别进行优先排序。项目团队表示很难知道接下来要做什么。因为很多条目被列为高优先级。项目经理应该推荐什么?An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority. What should the project manager recommend?


A.确保产品负责人根据产品路线图、发布计划和迭代计划来确定优先级。Ensure the product owner determines the priority based on a product roadmap, release plan, and iteration plan.

B.要求团队根据他们认为的逻辑顺序,对高优先级的项目进行优先排序。Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.

C.要求团队根据发布计划和最有效的测试方法来确定高优先级项目的优先次序。Ask the team to prioritize the high-priority Items based on the release plan and what allows to testing most effectively.

D.放弃当前需求的高、中、低分类,按数字排序。Discard the current categorization of requirements as high, medium, and low and prioritize numerically.


知识点:考前必刷题


参考答案:A


解析:产品负责人负责排列待办事项的优先级顺序,选A。

进入考试题库