主要干系人无法持续参加项目状态会议,项目经理已经与该干系人进行了非正式和定期的沟通,以确保干系人了解项目的最新情况,然而项目经理最近辞职,在离开之前不会与新项目经理见面,项目经理应该如何确保新的项目经理继续更新这个特定的干系人?The main stakeholders are unable to continuously participate in project status meetings, and the project manager has conducted informal and regular meetings with this stakeholder to ensure that stakeholders are updated on the latest developments in the project, the project manager has recently resigned and will not meet with the new project manager before leaving. How should the project manager ensure that the new project manager continues to update this specific stakeholder?


A.用干系人参与的具体信息更新沟通管理计划。Specific information update communication management plan for stakeholder participation.

B.根据干系人的具体沟通需求更新干系人参与计划。Update the stakeholder engagement plan based on the specific communication needs of stakeholders.

C.确保项目团队已经得到了关于该干系人的特定需求的指导。Ensure that the project team has received guidance on the specific needs of this stakeholder.

D.确保项目文件包含关于干系人的具体说明。Ensure that the project file contains specific instructions about the stakeholders.


知识点:考前必刷题


参考答案:A


解析:根据题干,了解到该干系人无法参加会议又需要让他了解项目情况,这时需要考虑沟通管理,沟通管理计划包括干系人的沟通需求,需沟通的信息项目,包括语言、形式、内容和详细程度等,所以选A。