一个软件开发供应商报告了一个阻碍其他剩余可交付成果的问题。项目经理应该怎么做?A software development provider reports an issue that is blocking the other remaining deliverables. What should the project manager do?
A.要求供应商寻求解决该问题的方案。Ask the provider to seek options to solve the issue.
B.把这个问题添加到问题日志中,并在下次评审会议上报告。Add the issue to the issue log and report it at the next review meeting.
C.审查当前计划,如有必要进行整合。Review the current plan and consolidate if necessary.
D.安排一次与供应商的会议,共同讨论解决方案。Schedule a meeting with the provider to collaborate on the options.
参考答案:D
解析:D选项最佳,项目经理应该首先向供应商了解问题情况,并找到解决方案。选项A错误,客户协作重于合同谈判。选项B错误,项目经理应该立即采取行动,而不是等到下次评审会议。