在项目实施过程中进行了对建议解决方案的概念验证,并确定当前的技术无法支持它。项目经理接下来应该做什么?A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology can not support it. What should the project manager do next?


A.请求另一名团队成员使用当前的技术重新进行概念验证,以确保这确实不是一个选项。Ask another team member to redo the nroot of concept using the current technology to ensure it is truly not an option.

B.使用根本原因分析(RCA)技术,如石川图,来确定为何当前的技术不支持。Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.把这个问题添加到问题日志中,并与团队探讨可能的解决方案。Add this item to the issue log and explore possible resolution options with the team.

D.更新风险登记册,表示必须由团队负责人选择新的技术。Update the risk register indicating that a new technology must be chosen by the team lead.


知识点:考前必刷题


参考答案:C


解析:关键词“当前的技术无法支持它”,这是一个问题,需要记录到问题日志中,并与团队一起讨论可能的解决方案,选C。