一个价值数百万美元的项目已经开始,并处于执行阶段。一个当地的监管机构刚刚宣布了一些需求的变更,这些变更需要在6个月内实施,也就是在项目执行阶段完成之前。项目经理接下来应该做什么?A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase. What should the project manager do next?
A.立即将新的需求添加到项目范围内,因为它们是强制性的变更。Add the new requirements to the project scope immediately since they are mandatory changes.
B.与合规部门一起审查新的需求,以确定是否需要进行变更请求。Review the new requirements with the compliance department to determine if a change request is needed.
C.忽略新的需求,因为当前的预算和进度不允许任何变更。Ignore the new requirements as the current budget and schedule do not allow for any changes.
D.按照已定义的项目需求进行,并延迟实施新的需求。Proceed with the defined project requirements and delay implementing the new requirements.
参考答案:B
解析:B选项最佳。根据整体变更控制程序,有新需求要变更,首先要了解情况,对其进行评估。选项A错误,范围变更需要走变更程序;选项C拒绝变更和选项D延迟变更不对。