When performing project activity duration estimates,( )is not included in the estimation techniques.
A.Three-point Estimating
B.Analogous Estimating
C.Parametric Estimating
D.Checklist Estimating
参考答案:D
解析:
在进行项目活动持续时间估算时,估算技术中不包括(清单估算)。
A.三点估算
B.类似估算
C.参数估计
D.清单估算