()is the process of implementing risk response plants,tracking identified risks,monitoring residual risk,identifying new risk,and ecaluating risk process effectiveness throughout the project.
A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management
参考答案:B
解析:
(控制风险)实施风险应对计划、跟踪识别的风险、监测剩余风险、识别新的风险以及评估整个项目的风险过程有效性的过程。
A. 识别风险
B. 控制风险
C. 计划风险应对
D. 计划风险管理